ECG begins 3hr power cut in parts of Accra for six days

0
20
Advertisement

The Electricity Company of Ghana (ECG) has begun a three-hour power cut to some parts of Accra for the next six days to enable it relocate transformers to a new site.

It said explained that as part of the relocation of 145MVA transformers from the Tema Port to the Pokuase Bulk Supply Point construction site, it will have to isolate some high voltage overhead lines.

Accordingly, electricity supply to persons in Tema, Klagon, Spintex, Trasacco, Dzorwulu, Achimota, and Ofankor will be cut from 10:00 p.m. to 1:00 a.m each day from Friday to next Thursday, May 14.

The Pokuase Bulk Supply Point is expected to supply and stabilise power and also reduce the technical and commercial losses of transmission to Pokuase, and its surrounding communities.

It is expected to directly benefit 350,000 people.

The $60 million dollar project was funded by the Millennium Challenge Corporation under the supervision of the Millennium Development Authority (MiDA).

By 3news.com|Ghana