E/R: Work on €70m, 600 bed Reg’l hospital progressing steadily

Google search engine

Work on the 70 million Euro, 600 bed Eastern Regional hospital is progressing steadily.

The first phase of 285 bed is 37 percent complete a year into the commencement of work, according to contractors of the project

The 36 months first phase according to contractors is on schedule .

the hospital set to cover a total floor area of approximately 20. Square meters

Upon completion, it will be fitted with administration, training, conference and teaching facilities; out-patient department; accident and emergency services; adjunct clinical services , pharmacy, imaging with Magnetic resonance imaging (MRI) and all modern facilities needed for a modern hospital.

The Eastern Regional Minister Seth Acheampong on an inspection tour of the facility says the NPP administration is focused on providing a world standard facility for the region and others.

Source: 3news.com|Ghana